This Order, which is made under section 3(1)(b) of the Transport and Works Act 1992, empowers the Environment Agency to construct a tidal barrier with a moveable gate across the river Orwell and to execute ancillary works, including dredging of the river. The Order confers the necessary powers on the Agency, including powers to acquire the requisite land and rights by agreement or compulsorily.
Lifecycle
Department
Made
16 Jul 2012
—
In force
07 Aug 2012
Enabling power
The Secretary of State in exercise of the powers conferred by sections 3(1)(b) and 5 of, and paragraphs 1 to 5, 7, 8, 10, 11, 13 and 15 to 17 of Schedule 1 to, the 1992 Act and by article 2 of the Transport and Works (Descriptions of Works Interfering with Navigation) Order 1992makes the following Order:—