The Bridgwater Tidal Barrier Order 2022
This Order authorises the Environment Agency (“the Agency”) to construct and operate a new tidal barrier with twin vertical lift gates across the river Parrett in Bridgwater, Somerset, together with a new building to enable operation of the new barrier, reinforcement of existing and construction of new flood defence embankments at Chilton Trinity, Pawlett and Combwich and to execute ancillary works.
Lifecycle
Department
Made
04 Mar 2022
—
In force
25 Mar 2022
Enabling power
The Secretary of State makes this Order in exercise of the powers conferred by sections 3(1)(b) and 5 of, and paragraphs 1 to 5, 7, 8, 10, 11, 13 and 15 to 17 of Schedule 1 to, the 1992 Act and by article 2 of the Transport and Works (Descriptions of Works Interfering with Navigation) Order 1992.