The Dogger Bank Teesside A and B Offshore Wind Farm (Amendment) Order 2024
This Order amends the Dogger Bank Teesside A and B Offshore Wind Farm Order 2015, a development consent order under the Planning Act 2008, following an application made in accordance with the Infrastructure Planning (Changes to, and Revocation of, Development Consent Orders) Regulations 2011 for a non-material change under paragraph 2 of Schedule 6 to the Planning Act 2008. This Order increases the maximum hammer energy limit from 1,900 kJ to 3,000 kJ for pin-piles required to install the Offshore Platform within Project A.
Lifecycle
Department
Made
11 Nov 2024
—
In force
12 Nov 2024
Enabling power
Accordingly, the Secretary of State, in exercise of the powers in paragraph 2(1) and (9) of Schedule 6 to the Planning Act 2008, makes the following Order.