BrowseStatutory InstrumentsSI 2019/669
SIin_forceSI 2019/669 · order

The Dogger Bank Teesside A and B Offshore Wind Farm (Amendment) Order 2019

This Order amends the Dogger Bank Teesside A and B Offshore Wind Farm Order 2015, a development consent order under the Planning Act 2008, following an application made in accordance with the Infrastructure Planning (Changes to, and Revocation of, Development Consent Orders) Regulations 2011 for a non-material change under paragraph 2 of Schedule 6 to the Planning Act 2008. This Order increases the permitted generating capacity to 1.4GW and the diameter of the blades on individual wind generators, alters the use of monopoles in Work No. 1B and imposes a requirement concerning the Southern North Sea Special Area of Conservation.

Sign in to trackLast fetched 30 Apr 2026 · legislation.gov.uk
Lifecycle
Department
Made
25 Mar 2019
In force
26 Mar 2019