The Dogger Bank Teesside A and B Offshore Wind Farm (Amendment) Order 2021

This Order amends The Teesside A and B Offshore Wind Farm Order 2015, a development consent order under the Planning Act 2008, following an application made in accordance with the Infrastructure Planning (Changes to, and Revocation of, Development Consent Orders) Regulations 2011 for a non-material change under paragraph 2 of Schedule 6 to the Planning Act 2008. The Order amends the limits on hammer energy during installation and makes some changes to the cabling descriptions within the array.

Sign in to trackLast fetched 30 Apr 2026 · legislation.gov.uk
Lifecycle
Department
Made
14 Jan 2021
In force
15 Jan 2021