BrowseStatutory InstrumentsSI 2016/49
SIin_forceSI 2016/49 · order

The National Grid (Hinkley Point C Connection Project) Order 2016

This Order grants development consent to National Grid Electricity Transmission Ltd (“National Grid”) for authorised works to the national electricity transmission system between Hinkley Point and Seabank. The proposed development is required to provide sufficient transmission capacity to enable the connection of new electricity generation projects in the region including the Hinkley Point C nuclear power station, and to carry out all associated works.

Sign in to trackLast fetched 30 Apr 2026 · legislation.gov.uk
Lifecycle
Department
Made
19 Jan 2016
In force
09 Feb 2016