The National Grid (Bramford to Twinstead Reinforcement) Order 2024

This Order grants development consent to National Grid Electricity Transmission plc (“National Grid”) for authorised works to the national electricity transmission network between Bramford Substation in Suffolk and Twinstead Tee in Essex. The proposed development is required to reinforce the existing electricity transmission network in East Anglia, and to carry out all associated works.

Sign in to trackLast fetched 30 Apr 2026 · legislation.gov.uk
Lifecycle
Department
Made
12 Sept 2024
In force
04 Oct 2024