The Willington C Gas Pipeline Order 2014
This Order authorises RWE Generation UK plc (the “undertaker”) to construct a cross-country pipeline of up to 800 millimetres in diameter (to be known as the Willington C Gas Pipeline) for the conveyance of gas and covering a distance of approximately 27 kilometres starting from the National Transmission System at Yoxall in East Staffordshire and ending at the proposed Willington C Power Station to be constructed at Willington in South Derbyshire, and to carry out all associated works.
Lifecycle
Department
Made
16 Dec 2014
—
In force
07 Jan 2015
Enabling power
Accordingly, the Secretary of State, in exercise of the powers in sections 114 and 120 of the 2008 Act, makes the following Order: