The Slough Multifuel Extension Order 2023
This Order authorises SSE Slough Multifuel Limited (referred to in this Order as the undertaker) to construct and maintain an extension to the existing Slough Multifuel combined heat and power generating station and to operate a generating station within the Order limits at a capacity of over 50MW (up to 60MW). This Order imposes requirements in connection with the authorised development.
Lifecycle
Department
Made
28 Nov 2023
—
In force
20 Dec 2023
Enabling power
The Secretary of State, in exercise of the powers conferred by sections 114, 115, 120and 140 of the 2008 Act, makes the following Order—