The North Blyth Biomass Power Station Order 2013
This Order authorises the construction and operation of a biomass fuelled electricity generating station and associated works to be situated at the Blyth Harbour Commission’s Battleship Wharf, North Blyth, in the County of Northumberland. It also provides for the connection of those works via a cable connection laid underground to the electricity distribution system. For the purposes of the development that it authorises, North Blyth Energy Limited is authorised by the Order to acquire land and rights in land compulsorily or by agreement as well as to override easements and other rights. The Order imposes requirements in connection with the development for which it grants development consent.
Lifecycle
Department
Made
24 Jul 2013
—
In force
15 Aug 2013
Enabling power
The Secretary of State, in exercise of the powers conferred by sections 114, 115, 120 and 149A of the 2008 Act, makes the following Order:
DocumentsOpen on legislation.gov.uk →