The Network Rail (Old Oak Common Great Western Mainline Track Access) Order 2026
This Order confers powers on Network Rail Infrastructure Limited (referred to in this Order as Network Rail) to acquire compulsorily a right over land and to use land temporarily, as well as to use the land within the Order limits as a construction compound, including provision of a temporary ramp, all in connection with the development of a temporary road rail vehicle access onto the Great Western Mainline railway to enable delivery of the Old Oak Common station and provision of a permanent maintenance access point for road rail vehicles onto the Great Western Mainline.
Lifecycle
Department
Made
03 Jun 2026
—
In force
24 Jun 2026
Enabling power
The Secretary of State in exercise of the powers conferred by sections 1 and 5 of, and paragraphs 2 to 4, 7, 8, 11, 16 and 17 of Schedule 1 to, the 1992 Act, makes the following Order.
DocumentsOpen on legislation.gov.uk →