The Meaford Gas Fired Generating Station Order 2016
This Order authorises Meaford Energy Limited (referred to in this Order as the undertaker) to construct, operate and maintain a gas fired electricity generating station of up to 299 MW. The Order would permit the undertaker to acquire, compulsorily or by agreement, rights in land and to use land for this purpose.
Lifecycle
Department
Made
19 Jul 2016
—
In force
02 Aug 2016
Enabling power
Accordingly, the Secretary of State, in exercise of the powers in section 114 and 120 of the 2008 Act, makes the following Order:
DocumentsOpen on legislation.gov.uk →