The Hornsea Two Offshore Wind Farm (Amendment) (No. 2) Order 2018
This Order amends The Hornsea Two Offshore Wind Farm Order 2016, a development consent order under the Planning Act 2008, following an application made in accordance with the Infrastructure Planning (Changes to, and Revocation of, Development Consent Orders) Regulations 2011 for non-material changes under paragraph 2 of Schedule 6 to the Planning Act 2008. The Order reduces from 6 to 3 the permitted number authorised offshore HVAC collector substations and expands the permitted size of the platform for each of those substations.
Lifecycle
Department
Made
04 May 2018
—
In force
08 May 2018
Enabling power
The Secretary of State, in exercise of the powers conferred by paragraph 2 of Schedule 6 to the Planning Act 2008, makes the following Order:
DocumentsOpen on legislation.gov.uk →