The Eggborough Gas Fired Generating Station (Correction) Order 2018
This Order corrects errors in the Eggborough Gas Fired Generating Station Order 2018 (S.I. 2018/1020), a development consent order made under the Planning Act 2008 (c.29), following a request under paragraph 1(5)(a) of Schedule 4 to that Act.
Lifecycle
Department
Made
06 Dec 2018
—
In force
07 Dec 2018
Enabling power
The Secretary of State, in exercise of the powers conferred by section 119 of, and paragraphs 1(4) and 1(8) of Schedule 4 to the Act, makes the following Order: