The East Anglia THREE Offshore Wind Farm (Amendment) Order 2019
This Order amends The East Anglia THREE Offshore Wind Farm Order 2017, a development consent order under the Planning Act 2008, following an application made in accordance with the Infrastructure Planning (Changes to, and Revocation of, Development Consent Orders) Regulations 2011 for a non-material change under paragraph 2 of Schedule 6 to the Planning Act 2008. Amendments to the Order include changes to the detailed offshore design parameters and an increase to the maximum generating capacity permitted for the development to 1,400MW.
Lifecycle
Department
Made
06 Jun 2019
—
In force
07 Jun 2019
Enabling power
Accordingly, the Secretary of State, in exercise of the powers in paragraph 2 of Schedule 6 to the Planning Act 2008, makes the following Order: