The Dogger Bank Creyke Beck Offshore Wind Farm (Amendment) Order 2019
This Order amends the Dogger Bank Creyke Beck Offshore Wind Farm Order 2015, a development consent order under the Planning Act 2008, following an application made in accordance with the Infrastructure Planning (Changes to, and Revocation of, Development Consent Orders) Regulations 2011 for a non-material change under paragraph 2 of Schedule 6 to the Planning Act 2008. This Order increases the permitted size of the diameter of the blades on individual wind turbine generators.
Lifecycle
Department
Made
09 Apr 2019
—
In force
10 Apr 2019
Enabling power
Accordingly, the Secretary of State, in exercise of the powers in paragraph 2 of Schedule 6 to the Planning Act 2008, makes the following Order: