The Burbo Bank Extension Offshore Wind Farm Order 2014
This Order grants development consent for, and authorises DONG Energy Burbo Extension (UK) Limited to construct, operate and maintain a generating station in the sea approximately 7 kilometres off the north Wirral coast, 8.5 kilometres from Crosby beach and 12.2 kilometres off the coast of Point of Ayr, Wales, being an extension to the existing Burbo Bank offshore wind farm located on the bed of Liverpool Bay, together with all necessary and associated development. The Order imposes requirements in connection with the development for which it grants development consent.
Lifecycle
Department
Made
25 Sept 2014
—
In force
26 Sept 2014
Enabling power
The Secretary of State, in exercise of the powers conferred by sections 114, 115, 120 and 149A of the 2008 Act makes the following Order—