The Building Safety (Description of Higher-Risk Building) (Design and Construction Phase) (Wales) Regulations 2023
These Regulations define what constitutes a higher-risk building for the purposes of section 120I of the Building Act 1984 (“the 1984 Act”). Part 3 of the Building Safety Act 2022 (“the 2022 Act”), which inserted section 120I into the 1984 Act, makes provision for higher-risk buildings to be subject to an enhanced regulatory regime during the design and construction phase.
Lifecycle
Department
Made
15 Nov 2023
—
In force
01 Jan 2024
Enabling power
In accordance with section 120A(9) of the Building Act 1984 a draft of these Regulations has been laid before and approved by a resolution of Senedd Cymru.
DocumentsOpen on legislation.gov.uk →