The Brechfa Forest West Wind Farm (Amendment) Order 2016
This Order amends the Brechfa Forest West Wind Farm Order 2013 (the “principal Order”), which granted development consent under the Planning Act 2008, following an application for a non-material change under paragraph 2 of Schedule 6 to that Act.
Lifecycle
Department
Made
10 Mar 2016
—
In force
11 Mar 2016
Enabling power
Accordingly, the Secretary of State, in exercise of the powers in paragraph 2(1) and (9) of Schedule 6 to the Planning Act 2008, makes the following Order:
DocumentsOpen on legislation.gov.uk →