The Ferrybridge Multifuel 2 Power Station Order 2015

This Order grants development consent for, and authorises Multifuel Energy Limited (referred to in this Order as the undertaker) to construct, operate and maintain, a new electricity generating station with a gross combined installed generating capacity of up to 90MWe fuelled primarily by waste derived fuels. The generating station is to be located at the Ferrybridge Power Station site, north-west of Knottingley, West Yorkshire. The Order also grants development consent for associated development and imposes requirements in connection with the development.

Sign in to trackLast fetched 30 Apr 2026 · legislation.gov.uk
Lifecycle
Department
Made
28 Oct 2015
In force
19 Nov 2015