The Electricity (Individual Exemption from the Requirement for a Transmission Licence) (Seagreen) (Scotland) (Amendment) Order 2025

The Electricity (Individual Exemption from the Requirement for a Transmission Licence) (Seagreen) (Scotland) Order 2024 granted an exemption to Seagreen Wind Energy Limited from the requirement to hold an electricity transmission licence in respect of Seagreen Offshore Windfarm. That Order provided for exemption until 7th February 2025. This Order extends the duration of that exemption until 31st March 2025.

Sign in to trackLast fetched 30 Apr 2026 · legislation.gov.uk
Lifecycle
Department
Made
09 Jan 2025
In force
08 Feb 2025