BrowseStatutory InstrumentsSI 2014/3328
SIin_forceSI 2014/3328 · order

The Willington C Gas Pipeline Order 2014

This Order authorises RWE Generation UK plc (the “undertaker”) to construct a cross-country pipeline of up to 800 millimetres in diameter (to be known as the Willington C Gas Pipeline) for the conveyance of gas and covering a distance of approximately 27 kilometres starting from the National Transmission System at Yoxall in East Staffordshire and ending at the proposed Willington C Power Station to be constructed at Willington in South Derbyshire, and to carry out all associated works.

Sign in to trackLast fetched 30 Apr 2026 · legislation.gov.uk
Lifecycle
Department
Made
16 Dec 2014
In force
07 Jan 2015