To ask Her Majesty’s Government what assessment they have made of the social and economic impacts of disruption to services following the withdrawal of some Hitachi high-speed trains being removed from service after defects were discovered in them.
My Lords, the vast majority of services across the national rail network are unaffected. The trains affected are Hitachi Class 800 series units operated by Great Western Railway on intercity services as well as some LNER services, Hull Trains services and a small number of TransPennine Express services. Most of the services used by schoolchildren and local workers are local services which have not been affected by this issue. The Government have asked operators to prioritise services used by schoolchildren where possible.
I thank the Minister for that Answer and I appreciate the amount of joint working that has taken place to enable some replacement services to run. The abrupt and total withdrawal of Hitachi trains from several routes caused massive disruption to passengers and businesses in some regions. It is an added blow to train operators, which had hoped to be attracting passengers back on to services. This is a crucial time as we establish fresh working patterns and the Government need to lure us back on to public transport. This appears to be an expensive design or manufacturing error.
Does the Minister agree that it is essential the cost is not borne by train operators, passengers or taxpayers? If so, are the Government in discussions with Hitachi about this issue? What steps do the Government intend to take to compensate the businesses and passengers affected? Does she agree that the Government need to fund a promotional period of reduced fares to attract passengers back on to the services, which have been so badly affected?
My Lords, the agreements in place to use the affected trains contain provisions that protect the taxpayer. We expect those who have contractual performance and train availability obligations to fully compensate the taxpayer.
My Lords, I am grateful to the noble Baroness, Lady Randerson, for asking this Question. I understand from the technical press that 86 out of 93 of these affected trains have either a failure of the yaw dampers, which connect the bogie to the body shell—they are quite important parts—or the lifting points, with cracks of up to one foot long. On the routes affected this clearly means that there are very few, if any, trains. These are trains designed and procured by the Government—
Unfortunately I missed the question, but I hope to provide some colour to what the noble Lord was saying. Indeed, there are two different types of crack. One is found on the yaw damper; those cracks were found three weeks ago and are not the reason for the withdrawal of the trains from service. The second cracks are on the lifting lugs and have led to the withdrawal of trains from service. I would like to reassure the noble Lord that there is a very stringent engineering risk assessment in place. These trains are checked every 24 hours and are being returned to service from today; we expect to have up to 25 coming back today. We hope that 60 GWR trains will be back by Monday and we believe that services will significantly improve.
The current situation has brought about an intolerable level of stress and inconvenience to the travelling public, not least here in Wales on the GWR routes. It is a relief that Hitachi has issued a statement this morning advising that a significant number of the IETs can return to service. What inquiries have been made of train leasing companies, such as Angel Trains and Porterbrook, to establish the possibility of recommissioning some of their redundant and in-storage HST 125 fleet to provide some alleviation of the current problem and possible future issues?
I would like to reassure my noble friend that I spoke to Mark Hopwood, the MD of GWR, this morning. He told me that the major routes of particularly high priority include those from south Wales and the south-west. We recognise that getting those services back is important. He is looking at other ways of procuring modern, clean rolling stock, although he pointed out that the return of HSTs is unlikely and he would hope to get more modern stock from elsewhere.
My Lords, the question of compensation arises here. Is there a liquidated damages clause in the agreement between the Government and Hitachi about these trains? If not, can Hitachi be pressed to make some ex gratia compensation payment for the huge damage that this delay is inflicting on both passengers and railway staff, through no fault of their own?
Of course, we are in conversations with Hitachi, and we welcome its decision to put safety first and take the trains out of service while we properly understand what is going on. As noble Lords will be aware, 122 Hitachi trains are procured via the intercity express programme, while the remaining 60 are under conventional rolling stock leases. We will look into what potential compensation may be forthcoming from Hitachi, but the train operating companies are offering refunds to their passengers for cancelled services.
My Lords, the noble Baroness and I were in happy agreement recently in your Lordships’ House about the fact that it was not necessary to copy France in limiting domestic air travel here because cities such as Manchester are closer and well connected by fast intercity services. However, of course, this utterly depends on reliable service—so is the Minister concerned that unreliability will inevitably force travellers back into their cars and on to still more polluting airlines?
No one wants to see a vast modal shift towards cars, but I accept that, in certain circumstances, when we have a situation such as this, that will occur. However, it is a very rare occurrence for this sort of wide-ranging manufacturing or other fault to be found in the make-up of the units. I am convinced that the Hitachi manufacturers are doing all that they can to get these units back on the rails, and I believe that services will be back to normal in the medium term.
My Lords, I declare an interest as a regular LNER user—indeed, I experienced disruption to the service on my trip down from Darlington. While it is essential that the defects are addressed, I am very aware of the jobs and investment brought to County Durham by Hitachi. Can the Minister confirm that this issue will not impact the investment in the region and the security of the jobs?
My Lords, in general, Hitachi trains have an incredibly good track record. Hitachi built the bullet trains in Japan, which, as noble Lords will know, have an exemplary safety record, and it has a very high engineering pedigree. While it will of course be up to Hitachi’s customers to decide where they make their purchases in the future, I for one believe that that sort of pedigree will not be diminished by these events.
Lord Rosser (Lab) [V]
What is the estimated likely total revenue loss following the withdrawal from service for repairs of the Hitachi trains? Who will foot the bill for that loss of revenue? I hope it will be neither the taxpayer nor passengers, and I would be grateful if the Minister could confirm that that is the position.