The right hon. Gentleman raises an important point. As I have always said from the Dispatch Box in this role, there is a balance to be struck here. We need to build nationally important infrastructure, and that does mean much more onshore wind in England to match the significant amount of onshore wind that has been built in Scotland over the past few years, including not far from my constituency. But the balance must be struck with protecting land as well. Even if we build the significant number of projects that are needed, there will still be protections for land in the areas he mentions. The planning system allows for those considerations to be taken into account.
The NSIP regime already includes nuclear and solar. We are saying that the ban on onshore wind introduced by the Conservatives was not a rational decision, so we are bringing it back into this process. [Interruption.] The shadow Minister says that it was absolutely rational, but his party’s former Energy Minister, the right hon. Member for Beverley and Holderness (Graham Stuart), said that it was “always mad”. I think we should remember that not everybody in the Conservative party agreed with it, including, I suspect, the shadow Minister himself.
Let me come to the second part of the statutory instrument: the question of solar. Solar has been subject to a 50 MW NSIP threshold since it was originally set out in the Planning Act 2008. However, much like onshore wind, solar panel technology has seen significant advances in efficiency, enabling a greater megawatt yield per site. Evidence suggests that the 50 MW threshold is now causing a market distortion. With modern technology, mid-sized generating stations have a generating capacity greater than 50 MW and therefore fall within the NSIP regime. That is likely to be disproportionate to their size, scale and impact. That has resulted in a large amount of ground-mounted solar projects entering the planning system artificially capping their capacity just below the 50 MW threshold, leading to a potentially inefficient use of sites and grid connections.