My Lords, I thank the Minister for the clarity with which the instrument was introduced. The capacity market has served us well, and we welcome this examination and updating of its functionality so that it can continue to do so long into the future.
From these Benches, the Liberal Democrats have long championed a decentralised, resilient and, above all, clean energy system. We recognise the necessity of the capacity market as a mechanism that keeps the light on during periods of high demand and low generation, and we support the broad thrust of these technical reforms. They should improve confidence that providers can deliver on their obligations, increase value for money and help to further integrate low-carbon technologies into the market. These regulations may be highly technical, but it is important that they are looked at closely, so I hope the Minister will forgive me in advance for asking a couple of technical questions from these Benches.
I welcome the Government’s intent to strengthen the delivery assurance. The 30% increase in termination fees, and in initial credit cover from £10,000 to £13,000 per megawatt, rising to £19,500 for new-build units that miss their 11th-month financial commitment milestone, is a reasonable restoration of real-terms value, given that these figures have not moved since 2016. I find it surprising that these instruments, which govern so finely balanced a market, have not been updated for over a decade. As I understand it, even with these new regulations, there is no standing process to ensure that future regular updates are in place. Were such processes contemplated and examined in the work that was done in preparing this? What guarantees do we have that we will continue to see future upgrades to this important marketplace?
The plan to suspend capacity payments the moment an insolvency termination notice is issued is good stewardship of public money, and we do not oppose it. I am, however, concerned that in seeking real-terms parity, these changes may inadvertently raise the drawbridge behind the incumbents already inside the market. A near doubling of credit cover for those who miss a milestone is a serious sum for smaller storage developers or for demand-side responses, even if it is entirely reasonable for a more established or bigger generator. What assessment has been made of the impact of these credit cover changes on the smaller and newer entrants and on the diversity of technologies bidding in future auctions?