My Lords, these regulations will make technical but important changes to the language used in existing legislation, bringing it into line with the new terminology and processes introduced by the Building Safety Act 2022.
I will start by providing some context for these regulations. After the Grenfell Tower tragedy, the Government recognised the need for an overhaul of our building safety regime. In 2017 we appointed Dame Judith Hackitt to conduct an expert review of the current regime. Her review identified the need for significant cultural and regulatory change, including recommendations focused on the building control process.
Part of the Government’s response to these building control recommendations included the introduction of provisions in Section 33 of the Building Safety Act that repeal Section 16 of the Building Act 1984. The Government consulted on these provisions, and they were subject to pre-legislative scrutiny ahead of formal consideration of the Building Safety Act.
Section 16 made provision for the deposit of plans with local authorities before starting building work, as well as the passing or rejection of the plans. The information provided to building control was not always consistent, nor always sufficiently detailed for the work to be carried out.
Section 33 of the Building Safety Act, which has yet to be enacted, repeals Section 16 and provides instead for a new system of applications for building control approval. For higher-risk buildings, this means a more stringent system, with the building safety regulator the sole building control body. Applicants cannot proceed with work without explicit approval from the building safety regulator.
For non-higher-risk buildings, there is no significant change from the existing procedure. Local authorities and approved inspectors will remain responsible for supervising this work, and work can begin before approval is granted. Applicants do so at risk of having to uncover or change work and could face enforcement action. In addition, provisions in the Building Safety Act largely transfer procedures for appeals under the Building Act from the magistrates’ court to the specialist First-tier Tribunal.
The purpose of these regulations is to align the Highways Act 1980, the Clean Air Act 1993 and 13 local Acts with the terminology and processes that will be established when Section 33 of the Building Safety Act is enacted. Provisions in the Highways Act that relate to the payment of charges for street works when building control plans are deposited are amended to refer to new systems of applications for building control approval. Section 16 of the Clean Air Act is also amended. This section requires local authorities to check the height of proposed chimneys to ensure that they are tall enough to prevent smoke and particulates becoming prejudicial to health. It is amended to replace references to the deposit of plans with provisions that refer to applications for building control approval.