With permission, I wish to take this early opportunity as Secretary of State to update the House on the Government’s progress on building safety and to set out this Administration’s approach. Two years on from the Grenfell tragedy, it remains our priority to ensure that we have a building safety system that people can trust. In taking on this role, I have been mindful of my responsibility to the bereaved and the survivors of that tragedy. We must support them to recover and rebuild their lives. I am pleased that we will have the continued support of my right hon. Friend the Member for Ruislip, Northwood and Pinner (Mr Hurd) as Minister for Grenfell victims. I am determined to play my part in their pursuit of answers and justice and to ensure that all residents of high-rise blocks of flats are safe, and feel safe, now and in the future. My predecessors have tackled that work with commitment and integrity, but having reviewed such matters since my appointment, it is clear to me that we must go further and at pace if we are to secure the system of building safety that we all want, so I will update the House on the immediate action that I intend to take.
First, I am consulting on changes to fire safety regulations for new build blocks of flats. We will seek to commit to requiring sprinkler systems as standard in a wider range of new flats. I am minded to reduce the height at which sprinklers are required down to 18 metres, but I am open to hearing evidence for other relevant thresholds and will be led by that evidence, wherever it takes us. We will also consult on requiring better signs and evacuation alert systems to support effective firefighting. I am grateful to the National Fire Chiefs Council and the London Fire Brigade for their valuable and continuing contributions. I have also published a summary of responses to our call for evidence on a full review of the technical requirements in approved document B. There will likely be additional changes in due course. When taking such decisions, we will always be led by the evidence and residents’ safety. I will keep the industry and Parliament informed.
Secondly, with respect to the “Building a Safer Future” consultation, I intend to respond by the end of the year and to legislate at the earliest opportunity. I believe that we should establish a new building safety regulator to oversee the new regulatory regime for buildings. However, it is clear that we need to act now, so we are working with the Health and Safety Executive to use its experience to set up the regulator in shadow form prior to new legislation, and I want to see that happen as soon as practicable. We will take decisions on the regulator’s long-term functions and structure during the autumn. Again, I will update the House accordingly.
Thirdly, although the answer to the concerns of residents is the establishment through legislation of the new safety case regime, with the individual assessment of buildings envisaged by Dame Judith Hackitt, it is clear that we should not wait until then to act.
The Home Secretary and I have worked with the National Fire Chiefs Council and intend to establish a new protection board, which will provide expert and consistent inspections across the country to ensure we are identifying, managing and properly recording risks. This will significantly increase the pace of inspection activity across high-rise residential and other high-risk buildings to make sure building owners are acting on the very latest safety advice.
I expect all high-rise buildings to have been inspected or assured by the time the new building safety regime is in place, or no later than 2021. Residents of these buildings should be swiftly informed of the results of those assessments and inspections, with any changes acted upon as soon as possible.
Improved inspection activity for non-ACM high-rise buildings will be informed by local authorities’ current data collection work. Today, to support that work, I am pleased to confirm that we are providing them with £4 million of additional funding. I can also confirm that my Department will provide £10 million a year of additional funding to help local authorities improve their inspection capabilities and to support the work of the protection board, which we are now launching.
Should the protection board consider it necessary, I will, of course, consider providing additional resources during the remainder of this financial year to increase the pace of inspection and assurance work. I hope this systematic inspection programme will provide reassurance to residents across the country, many of whom I understand have legitimate concerns.
Finally, on our ongoing work to support the remediation of dangerous ACM cladding on buildings, where it poses a clear risk, the Government made funding available in May for its removal from eligible buildings in the private residential sector, in addition to funds already available for the social sector, bringing the total to £600 million.
As of 12 September, eligible private sector building owners will now be able formally to submit their applications for funding for ACM removal and replacement. They have until the end of December to apply. There is no excuse for building owners to delay. My Department has been encouraging swift applications, and we now have a direct relationship with a named individual in the United Kingdom for each relevant building. Where we receive applications, we will do everything we can to turn them around rapidly, prioritising and considering responses on a rolling basis.
Let me be clear: inaction will have consequences. I will name and shame individuals and businesses if I see inaction during the autumn. If we reach the end of autumn and building owners have not responded, and do not have exceptional reasons for it, I will take whatever steps and sanctions are necessary. I will support local authorities to take robust enforcement action against reluctant building owners, and I have asked the joint inspection team to provide them with all necessary advice.
Failure to act, particularly now that the funding is provided by the taxpayer, would be frankly disgraceful, and I know colleagues in this House will share that determination. Where Members have ACM-clad buildings in their constituency, we will provide guidance on how they can encourage building owners to apply. My Department stands ready to advise on the contact we have had already.
With regard to non-ACM cladding, the research programme began in April 2019 and scheduled testing has now concluded. Findings will be published in the autumn. Following the full report, the expert panel will consider whether further testing should be commissioned or existing advice supplemented. The panel anticipates that it will publish any such additional advice by the end of this year. In the interim, building owners should continue to follow the very clear steps set out in advice note 14 to ensure the safety of their buildings and residents.
The safety of people in their home must be paramount. I hope the House will welcome the measures I have laid out today to ensure that no one should feel unsafe in their home and to build a safety system that people across this country can trust.
I commend this statement to the House.