That this House has considered the future of the Ajax Programme.
It is a pleasure to serve under your chairship, Mr Stuart. This debate has been a long time coming. Such is the Kafkaesque procedure for selecting debates that this application was granted only at the eighth time of asking; I had first requested a debate on this subject on 1 September 2025—over four months ago. Since then, the Ajax programme has gone from on track to throwing a track, and the outlook for the programme and our armoured capability, the future of armoured infantry as a concept and the current deployability of 3rd (UK) Division are now all very much under the microscope.
In this debate, I am not seeking to apportion blame, point fingers at individuals or orchestrate a witch hunt. It is clear that the Ajax programme has been failing for a number of years, although I will go on to question some of the recent specific decision making regarding the programme. Accountability sits with successive Ministers. The slow progress on delivery appears to be an issue between the Army, the Department and General Dynamics.
We can skip over the potted history of the Ajax programme—others will cover that—but, to paraphrase Rodgers and Hammerstein, “How do you solve a problem like Ajax?” Although it was based on an existing General Dynamics platform, the Army made so many additions and revisions to the existing capability that it is now considered to be bespoke technology. We are talking about a staggering 1,200 capability requirements for each of the six vehicle types under the Ajax umbrella.
The March 2022 National Audit Office report on the Ajax programme details the fact that neither the Department nor General Dynamics fully understood some component specifications or how they would be integrated on to the Ajax vehicle, leading to consequential changes to the overall design, disputes between the Ministry of Defence and General Dynamics and, inevitably, programme delays. Both the MOD and General Dynamics have been criticised for underestimating the scale of the work, the technical challenge and the sequencing of the work. General Dynamics blamed the MOD for not having fully defined acceptance criteria; the MOD blamed the General Dynamics safety documentation. The contingency within the programme was quickly used up and the programme was suddenly four years behind schedule.
Noise and vibration issues were recognised in mid-2020, with a stop notice issued in June 2021. All dynamic movement and transition activity was halted while the programme underwent a significant reset. The Army resumed training on Ajax in 2023, but paused again in November 2025. The programme’s issues from 2020 to 2021 are well documented. Those issues are a failure to establish effective governance, complex assurance arrangements, high turnover of senior staff, an ineffective programme board, weak project controls—the list goes on. The most stark, however, was
“an over-emphasis on achieving its IOC”—
initial operating capability—
“target date, which meant that it prioritised time and cost over capability. As a result, it pressed ahead with the programme without resolving performance issues.”
Given what we know now and the issues encountered less than three weeks after IOC was declared, I would like to hear an assessment from the Minister as to whether he believes that that is still an issue today.
Initial operating capability for the Ajax programme was declared on 5 November 2025 by the Government; I stress “by the Government”, because several stages to that process were not made public until last month. The Minister for Defence Readiness and Industry confirmed to me:
“All criteria for Ajax Initial Operating Capability…were met on 23 July 2025 and following a period of review, IOC was declared by the Army on 15 September 2025.”
We know that only because it was written on a cake in a General Dynamics promotional video of the Minister’s visit to Merthyr Tydfil. Additionally, he confirmed:
“Before declaring Initial Operating Capability, I received written assurances from the Chief of the General Staff and the acting NAD”—
national armaments director—
“that the vehicle was safe to operate. Within the letter note AJAX the vehicle was described as ‘demonstrably safe to operate’.”
The Minister added that
“prior to Ajax Initial Operating Capability being announced, I sought assurances in writing from the Chief of the Defence Staff and the National Armaments Director that the system was safe to operate, which I received.”
I thank my hon. Friend for initiating this important debate. Does he agree with me that it is important for the Minister to set out that in 2022 I and colleagues on the Defence Committee went to Merthyr Tydfil, did a review and clearly stated that IOC was nowhere near deliverable in the timeframes proposed? Does my hon. Friend think it is worth the Minister setting out what checks against the Defence Committee report were done when looking at IOC?
I thank my hon. Friend for that excellent point. I was not going to cover it in my speech, so it is definitely worth adding to the record for the Minister to address in his response.
The interim National Armaments Director, the new National Armaments Director, the Chief of the General Staff and the Chief of the Defence Staff represent our most senior leaders within defence. It is hard to believe that they all would have signed off a vehicle platform that was inherently unsafe or where it was a sketchy 50:50 decision. How did we reach a point where four-star senior officers and equivalents had the confidence to sign off the vehicle’s initial operating capability, which then received ministerial approval, only for it to blow up in everybody’s face weeks later like a Wile E. Coyote Road Runner trap?
The March 2022 National Audit Office report states:
“The Department believes that the contract also incentivised GDLS-UK to prioritise production milestones over the quality and performance of the capability.”
It goes on:
“The contract incentivised GDLS-UK to achieve production milestones resulting in it continuing to manufacture vehicles while technical issues remained unresolved.”
Can the Minister give any clarity on whether that is still the case today, given that General Dynamics signed off achieving all the criteria required to meet initial operating capability, only for the entire programme to collapse less than four months later? Initial operating capability was also signed off by the Army on 15 September, before ministerial sign-off was granted on 5 November.
Last year, the then Minister for Defence Procurement and Industry stated that
“The Armoured Cavalry Programme (Ajax) is projecting the delivery of over 180 operationally deployable platforms by the end of 2025.”
My hon. Friend is making an excellent speech. On Boxer specifically, just before Christmas I received an answer to a parliamentary question from the Department, saying that it now will not give the initial operational capability date for Boxer, and that it is subject to the long-awaited defence investment plan. Does my hon. Friend agree that Boxer has already slipped by years, and that we cannot let it slip any further?
I absolutely concur with my right hon. Friend that Boxer is a vital capability—even more so, given the training pause that we are now encountering with Ajax—and we need to get Boxer into service as quickly as possible. I welcome the speeding up of that process overall.
Meanwhile in October, the then Minister for the Armed Forces had stated:
“Currently ARES will be fielded to Training Regiments, Armoured Cavalry units and Armoured Infantry units.”
As I said, we have ordered only 93. For reference, in order to reflect the establishment of an armoured infantry battalion, we would need 45 Ares to replace the capacity of the Warrior FV510, notwithstanding how many Athena variants we would need to cover the 511 command variant. Where is the capacity to have vehicles at training regiments and armoured cavalry units? There is no redundancy built into the current vehicle fleet.
The 93 Ares platforms equate to just 23 per battalion with no spare capacity, which is not even enough to replace three rifle companies’ worth of the Warrior FV510 variant. Can the Minister explain what the future establishment of these armoured infantry battalions will be? I appreciate that he will not have that information to hand—I do not think the Army knows yet—but will he write to me and explain how an armoured infantry battalion will be structured using Ares and Boxer?
The demise of Warrior leaves a yawning capability gap that will be difficult to adequately replace without a new IFV. The then Minister for the Armed Forces stated that,
“there is no direct replacement for Warrior”,
and:
“There are no plans to extend the out-of-service date for Warrior beyond 2027, and as such an extension is not under consideration.”
I thank my hon. Friend for his generosity in giving way. As well as the delays to Boxer, there are now strong rumours about further delays to the upgrade of Challenger 2 to Challenger 3. As Rheinmetall BAE Systems Land is responsible for both programmes, does my hon. Friend agree that it really needs to sort itself out and get on with it?
I thank my hon. Friend again, and I absolutely concur. With the delays to Ajax, we can no longer afford to fail to upgrade Challenger 2 to Challenger 3. The fact that the timeline of that has slipped to indefinite is a serious concern for our armoured capability.
A successful export programme would fuel development of the platform and allow it to improve over multiple iterations. It would enhance our own capability, and allow us to benefit from the first-mover advantage of adopting a common vehicle platform that can be expanded with the addition of an IFV and a mortar variant, putting us in the vanguard of armoured development in the drone age. But that cannot happen without the vehicle proving its capability—first with the soldiers, then with our allies. In a crowded field, that should be a top priority.
In “The Iliad”, Ajax loses a competition to Odysseus and, distraught by the result and conquered by his own grief, plunges his sword into his own chest, killing himself out of shame at his own failure. The irony should not be lost on any of us. Fix Ajax, and fix it quickly. There is a war coming.
It is a pleasure to serve under your chairmanship, Mr Stuart. I congratulate the hon. Member for Huntingdon (Ben Obese-Jecty) on securing this important debate. My constituency is home to General Dynamics, and its site at Pentrebach is where Ajax vehicles are currently assembled. I am here today to try to represent the views of the 700 or so workers at the site, many of whom are my constituents.
In relation the concerns raised in November, as I said in the Chamber following the recent urgent question, safety is the priority and of paramount importance. It is essential that everything possible is done to keep our brave servicemen and women safe. I am aware that General Dynamics is working closely with the Government and the MOD to try and get to the bottom of what happened in November and put right anything that needs to be in response. Since initial concerns were identified in 2021, the company has worked closely with the Government and robust testing has been carried out over a number of years by the company together with the MOD and the Army.
General Dynamics has operated in south Wales valleys for many years and acquired the site in Merthyr Tydfil in 2014. Since then, hundreds of my constituents and others from surrounding areas have been employed on the Ajax programme and have dedicated themselves to playing their part in building a platform that is at the forefront of our defence readiness. Just two months ago, the Minister for Defence Readiness and Industry was in Merthyr Tydfil to celebrate the milestone of the IOC being awarded. I was present that day and the whole workforce was upbeat about the contribution that it was making to the nation’s defence story.
General Dynamics has been committed to the local area, and I am aware that there are ongoing discussions around export of the Ajax platform to other countries. This, of course, would mean sustaining jobs and creating additional jobs in my constituency and in the supply chain across south Wales and beyond.
Many of my constituents are employed in this sector, by General Dynamics and in the wider supply chain. Would my hon. Friend agree that those are the very types of secure, well-paid jobs that we need across the south Wales region?
I absolutely agree with my hon. Friend’s comment. It is important that we have certainty for those jobs and sustain and increase such jobs across south Wales, because that is integral to this Government’s growth agenda in communities in Wales and across the UK.
Merthyr Tydfil has a long, proud and historical association with the defence of our country. Merthyr was the largest iron-producing town in the world at the time of the industrial revolution, producing cannons and cannonballs for the Royal Navy, leading to a visit from Admiral Nelson himself in 1802 to the Cyfarthfa ironworks. Our area is keen to renew that role in the 21st century and play a part in creating quality defence capabilities with our dedicated and committed workforce.
As I mentioned earlier, currently more than 700 people are employed at the site and those skilled and long-term employment opportunities are vital to the ongoing regeneration of the valleys—an area where heavy industry, such as coal mining and steel, has now ceased, and new industry and employment opportunities are so important to creating hope and growth in our communities. In addition, as a proud supporter of the Union of the United Kingdom, it is hugely important that people across the whole of the UK feel included in the defence sector and ongoing Government investment in the defence capability should benefit communities in the UK and particularly the south Wales valleys.
In closing, I ask the Minister to address a few points. While I fully appreciate that the investigation has to take its course, does he have any indication of what timescale is in place for the investigations to be concluded? The longer the uncertainty goes on, the more impact it will have on the morale of the workforce in Merthyr Tydfil.
Finally, while I appreciate that the Minister is responding on behalf of the MOD, in the Chamber last month, I asked the Minister for Defence Readiness and Industry if he would meet staff and trade unions at General Dynamics as soon as possible to provide them with as much reassurance as possible, something he committed to doing. Today I ask the Minister if he will undertake to raise with the Minister for Defence Readiness and Industry the importance of that visit taking place at the earliest opportunity. In the event that the investigations take longer than expected, will he commit in the meantime to asking the MOD to find a way to provide regular updates to the staff and workforce until more certainty can be provided?
It is a pleasure, as ever, to serve with you in the Chair, Mr Stuart. I thank my hon. and gallant Friend the Member for Huntingdon (Ben Obese-Jecty) for securing this debate today.
As has already been laid out, the Ajax programme has been a disaster. It has been repeatedly delayed and enormously expensive. We have known for years about problems with noise and vibration. It is mystifying how these vehicles were signed off as safe, despite so obviously not being so. British soldiers have been permanently injured as a result. Clearly the problems with Ajax did not begin under this Government; the vehicles were expected to be combat ready by mid-2019. However, the decision about what to do with the programme now does fall to this Government. Whatever they decide, this debacle cannot be allowed to continue.
The programme’s consistent failure sends a clear signal to those who have committed their lives to serving our country that, while they may be doing their duty to this country, the British Government are not performing their duty to them. How else are our armed forces personnel supposed to interpret a programme that has been repeatedly delayed, has racked up enormous costs and, as we heard last year, poses a direct risk to soldiers? When we ask people to put their lives on the line to protect our freedoms, the very least we can do is provide them with functional equipment, on time, that does more harm to the enemy than to our own troops.
The Ajax programme does an appalling disservice, not just to Britain’s armed forces—although that is awful—but for British taxpayers. The programme has a budget of £6.3 billion, enough to pay for the running of every court in England and Wales for two years. It is £6.3 billion of people’s hard-earned money. These vehicles do not work, and I would like my money back.
If Ajax was the only failure, that would still not be acceptable, but it might at least be written off as an aberration. However, the pattern of the British Government failing their duty to the armed forces is, sadly, far more widespread. In March 2024, a former armed forces Minister told the House of Commons that the British Army’s ammunition stockpile would be exhausted in just 10 days of warfare. The Ministry of Defence has said it believes we will need to spend an additional £28 billion to meet its costs over the next four years—yet at the Budget just two months ago, defence spending rose by £500 million less than was projected in the summer.
It is a pleasure to serve under your chairship, Mr Stuart. I congratulate the hon. Member for Huntingdon (Ben Obese-Jecty) on introducing the debate, and thank him for his service in the Royal Yorkshire Regiment. May I take the House back to a visit I made to the NATO Forward Land Forces contribution as part of Operation Cabrit? I spent time in a Challenger 2 tank, and what was most impressive was not the size, the armour or the firepower, but the complete confidence that its crew had in the vehicle. Ajax was meant to deserve and earn the same trust. Before I come on to the failures in the programme, however, I want to say something about the workers in south Wales: they deserve credit for their graft and determination, not blame.
The Public Accounts Committee, of which I was previously a member, has made it clear what went wrong. It found that the programme was over-specified from the outset, with about 1,200 individual requirements imposed on what was supposedly an adapted off-the-shelf design. In reality, Ajax was neither off-the-shelf nor fully bespoke, and what was in between was far riskier. Never again must defence procurements over-specify requirements; that should be a red flag right from the start. Computer models were relied upon to assess vibration and noise rather than vigorous early testing. The Public Accounts Committee found that that approach had failed, and that the Department at the time did not fully understand the vehicle’s characteristics before subjecting soldiers to trials. Our armed forces should never have been used as human guinea pigs.
The independent Sheldon review is more damning: it found a culture in which bad news was softened as it travelled up the management chain. Senior leaders were left without a clear, honest picture of what was really happening. I thank all the soldiers who stepped forward to raise safety concerns. Despite the warnings that were given, the safety notices that were issued and the whistleblowers who came forward, GD repeatedly underplayed the scale of those issues, so it is reasonable to ask a simple question: if the design ultimately lay with the contractor, would the chief executive officer of GD be happy to have their son or daughter sent on to a battlefield in an Ajax? If those design failures did rest with GD, the taxpayer should not be left carrying the cost of retrofit.
It is a pleasure to serve under your chairmanship, Mr Stuart. I thank my hon. and gallant Friend the Member for Huntingdon (Ben Obese-Jecty) for securing this important debate.
I want to briefly link the lessons of Ajax to wider concerns in MOD procurement. My hon. Friend has frequently mentioned the Boxer; having met with a key local manufacturer in my constituency, I have been made aware of the potential implication of issues with the UK Boxer mechanised infantry vehicles and Project Hunter, the procurement of laser protection and signature reduction systems under the alternative individual weapon programme. It is essential that we are agile and apply the lessons of Ajax to other such procurements. That is important locally in my constituency, since Royal Marines 42 Commando are based there and are potential customers of some of the equipment, and it is important nationally to make sure we ensure value for money, national security and operational capability.
The business in my constituency has raised issues with the Boxer, such as the procurement and performance of the periscopes, the driver’s modules and the mission module. These have been raised with Rheinmetall BAE Systems Land, the prime contractor; with GuS Periscopes UK, the supplier; with the relevant defence equipment and support teams; with UTAC; with local MPs, one of whom is the Minister for Defence Readiness and Industry and another of whom serves on the Defence Committee, and with the Secretary of State for Defence. To date, no response has been received. I raised a question in the recent Ajax statement and the Minister for Defence Readiness and Industry was interested I am waiting for a response from him to agree a meeting. Ultimately, we need to ensure that we take lessons from Ajax and speed up talking about the potential issues with Boxer as well.
Project Hunter was designed to procure up to 10,000 KS-1 rifles for our military over a 10-year period. Included was an optical scope with a laser protection system, and a noise and muzzle flash suppression system. To date, of the significant number of rifles procured, zero have been equipped with that system. We have heard from Ukrainian veterans’ charities that up to 360 snipers have been blinded as a result of using that equipment—something we should be taking very seriously. The implication, if funding is not allocated for this promised addition to the weapons, is that we will not have the laser protection system. That would leave our soldiers vulnerable to offensive countermeasures and risk significant injurie; due to the reflective nature of unprotected sighting systems, the threat of counter-detection would also be significantly higher as it would allow opposing forces to target our soldiers.
20 of 51 shown
Despite the various travails of the Ajax programme, production has continued throughout the training pause. As a result, we know that the Army has received just under a third of all Ajax platforms across all variants. It should be noted that the 2022 National Audit Office report highlighted that the compressed programme schedule flagged that there would no longer be time to validate the design of capability drops 3 and 4 before manufacture. Given that we are now in capability drop 3, can the Minister confirm whether the designs were validated before these vehicles were assembled and delivered last year?
The Minister also confirmed that
“It is anticipated that a further 110 platforms will be delivered in 2026, with the remaining 297 platforms delivered by 2028.”
With 180 Ajax platforms delivered, a similar number still to be accepted by the Army and all 589 hulls having now been completed in Spain, on current timelines the complete production run will have been completed by mid-2027. I believe that includes bringing all vehicles up to capability drop 4 standard.
Assuming that any resolution to the current training pause does not involve the mother of all factory recalls, there could potentially be an idle factory in Wales. What plans are there for the Merthyr Tydfil factory beyond the middle of next year? With only 18 months’ work left to complete, can the Minister assure General Dynamics employees in Wales that they will have a job once Ajax production is complete? Can he assure those employees that there will be no redundancies, given that we have no plans to purchase any more vehicles and that export plans are yet to materialise? While I appreciate that UK Defence and Security Exports sit within the Department for Business and Trade, can the Minister confirm what progress UKDSE has made regarding any potential export sales?
One of the main reasons why we are debating this topic today, and the reason for such media interest, is the social media content that has emerged from the factory and from Army personnel regarding the workmanship on the vehicles. To that end, I would like to recognise the efforts of Alfie Usher, aka Fill Your Boots, who has been instrumental in putting heat and light on this issue on behalf of service personnel. For obvious reasons, I am no trade unionist, but he has been the unofficial secretary-general of the unofficial armed forces union for some time.
I know that the Armed Forces Minister has previously liaised with Alfie on issues, and—I say this only partially in jest—perhaps the Government should reconsider his application to be the Armed Forces Commissioner. The Government are struggling to fill the role. Alfie’s application got binned back in August, but he has been doing the job unpaid since then anyway.
For those who do not follow Alfie’s account—any politician with an interest in defence really should—I should say that between the exposés and topical memes, Alfie has been the bête noire of General Dynamics and the Army, operating as chief whistleblower and ensuring that the voice of those on the ground can be heard. There have been multiple examples of concerns shared by him via social media on behalf of service personnel tasked with prepping newly delivered vehicles. A variety of issues have been highlighted and I ask the Minister, if he has not done so already, to include Alfie within the scope of the ministerial-led review to ensure full transparency and the inclusion of service personnel. They are the end users of this vehicle, and too often we ask our personnel to put up and shut up. An organisation that dines out on moral courage and pretends that it values 360° feedback should make sure that it listens to our soldiers, irrespective of how refreshingly blunt their views might be.
The evidence shown by Fill Your Boots has put heat and light on the production and assembly issues upon which blame has been placed. During the first pause in 2021, the MOD and General Dynamics did not agree on whether the levels of noise and vibration of Ajax vehicles breached contractual requirements. Given that the same noise and vibration issues potentially remain unresolved six years later, can the Minister clarify what does constitute a contractual breach?
Through 2020-21, General Dynamics undertook a supposedly in-depth review of the Ajax programme to confirm the root cause of noise and vibration issues, identify solutions and then validate them through extensive testing. They identified that noise and vibration issues were caused by the track, suspension and running gear; the engine and its mounting in the vehicle; quality issues including bolting, cable routing and welding; and performance and integration of crew headsets. The vehicles were thoroughly assessed using a noise and vibration calculator, whatever that is, to determine
“the safe operating envelopes for the platform across different speeds and terrains.”
The noise and vibration calculator provided by General Dynamics did not measure noise and vibration, which the Defence Science and Technology Laboratory raised concerns about. It estimated the maximum safe exposure time on Ajax vehicles for given conditions based on measurements from early trials. In August 2020, the first noise-induced hearing loss symptoms were reported by soldiers. In September 2020, DSTL discovered an error in General Dynamics’ measurements, which meant that vehicle crews might have been overexposed to noise and vibration. The Minister for Defence Readiness and Industry has told me:
“Whole Body and Hand Arm Vibration Levels were well understood, and effective mitigations were in place.”
But they cannot have been effective, or why would personnel still be suffering from noise and vibration-related sickness? Will the Minister confirm that any analysis of the root cause of the current noise and vibration sickness does not use the General Dynamics noise and vibration calculator, and instead seeks to use a metric that does not raise concerns with DSTL?
The measures implemented by General Dynamics included the implementation of an effective hearing protection and combined communication system, an improvement to the overall Ajax build quality, a review and amendment of build tolerances for key crew interfaces, changes to seat structures to provide greater vibration attenuation—that sounds very much like new seat cushions—and improvements to track tensioning procedures to ensure correct track tension, which reduces vibration.
On the track tension, I am aware that composite rubber tracks are now mature enough to be viable for a vehicle the weight of Ajax. Although there are still issues regarding track replacement, given that the whole track has to be replaced rather than a single track link, I note that the General Dynamics Ajax Blackjax demonstrator vehicle at DSEI had this fitted. I ask the Minister what assessment his Department has made of the feasibility of switching to composite rubber tracks as a potential solution going forward?
The 2022 National Audit Office report outlined that there were 27 limitations of use on Ajax vehicles in September 2021; 22 were safety-related and 11 were critical to achieving IOC. Can the Minister give the House assurances that those 11 limitations were resolved prior to initial operating capability being declared in 2025? Could the Minister also confirm what contractual payments were made to General Dynamics on the achievement of the criteria for initial operating capability in July 2025 or the formal declaration of initial operating capability on 5 November 2025? What is the total amount paid to General Dynamics as of today, and how much still remains to be paid? What delivery milestone will trigger the remaining payments?
With those resolutions to the previous issues identified in mind, we know that three exercises took place between IOC criteria being achieved on 23 July and ministerial IOC declaration on 5 November. We have not heard of any instances of noise and vibration sickness occurring among vehicle crews during those three exercises. Will the Minister confirm that there were no noise and vibration sickness issues among crews during those three exercises?
I asked the Minister for Defence Readiness and Industry what discussions his Department had had with General Dynamics, the senior responsible officer and the British Army regarding the Ajax programme between 23 July and Exercise Titan Storm in late November. Instead of a response, the Minister told me:
“I have directed a Ministerial review that covers elements of his question. I will update the House in due course.”
The Minister was happy to tell me that he met with key stakeholders, including meeting General Dynamics after the programme was paused, but, much as I have tried, the Government have scrupulously avoided disclosing any information about what ministerial discussions have taken place with stakeholders between 23 July and 5 November.
On 1 January, I asked a named day question for answer on 7 January 2026. I asked:
“how many noise and vibration injuries were sustained…between 23 July 2025 and Exercise Titan Storm”.
Strangely, I have not received a response yet, a week after one was due—it is almost as if this is an issue that the Government do not want to disclose. Will the Minister clarify the answer to written question 101920 and put on the record how many noise and vibration injuries were sustained between the achievement of initial operating capability criteria by General Dynamics and the start of Exercise Titan Storm?
The March 2022 National Audit Office Report states that the Department
“knew of noise and vibration issues before soldiers reported injuries but was not aware of the severity of potential problems. Reporting of issues identified in trials was limited and slow, meaning that safety concerns were not shared or escalated by the Army or…DE&S”.
Has that culture been addressed? Concerns were first raised about noise and vibration by the Army trials team in late 2019, but did not appear in quarterly programme reports until March 2021. To what extent have we seen the same issue repeat itself last summer?
In December 2025, the Minister for Defence Readiness and Industry confirmed to me that
“Of the 61 vehicles of all AJAX types involved in the exercise, 23 AJAX Vehicles were linked to soldiers suffering from noise or vibration injury.”
I would be grateful if the Minister confirmed where those 61 affected vehicles were manufactured. Were they part of the first 100 Ajax vehicles manufactured and assembled in Spain, or were they later vehicles whose hulls were manufactured in Spain but were assembled at the Merthyr Tydfil facility? Can he also confirm whether the early production vehicles from capability drop 0 to 2, which were identified as not being fully compliant with requirements, have now been retrofitted and what capability drop are they currently equipped to?
The Minister also confirmed that
“On 22 November…during a routine training exercise, around 30 soldiers operating in Ajax reported being affected by noise and vibration exposure.”
For 30 soldiers to be affected by the same noise and vibration sickness, with identical symptoms, as a result of a known issue supposedly resolved by 2023 is simply unacceptable. It is incredibly important that we are able to understand whether there were any instances during the three exercises prior to Titan Storm and indeed to identify whether there have been any instances of General Dynamics employees affected by noise and vibration exposure during the same period, prior to or after the 23 July IOC criteria achievement milestone.
In November, I asked the Minister for Defence Readiness and Industry how many compensation claims related to noise and vibration symptoms incurred during the use of Ajax variants had been made since the start of the armoured cavalry programme. The Minister informed me that it would take time to collate and review the information needed to answer the question, and that he would write to me. It is now mid-January and I would appreciate it if the Minister could provide that information in his response. It should not take two months to work out how many compensation claims have been made relating to Ajax. If I were Minister, I would have a close eye on the running tally, particularly in preparation for this debate.
On 8 December the Minister confirmed:
“We are currently undertaking reviews into the medical injuries sustained by Ajax crews, and more details on the findings will be published in due course.”
Will the ministerial-led review he has commissioned or the report from the Defence Accident Investigation Branch contain the details of those findings? In that review, will he confirm how many service personnel are undergoing treatment or have been diagnosed with hearing loss following audiometry protocols after operating within an Ajax variant?
Regarding when the vehicles will be able to recommence training, any decisions on the pause are to be made by Ministers after the investigations by the Defence Accident Investigation Branch have concluded. That suggests that the pause will be lifted after the investigation but before the conclusion of the ministerial-led review. Will the Minister clarify the timeline for the investigation, which he previously stated would take at least two weeks and so should be approaching conclusion, and the ministerial-led review, for which we are yet to see the terms of reference, which were due before Christmas? I appreciate it will still be autumn until the defence investment plan is published in March. Will the pause on the use of Ajax be lifted before the conclusion of the Minister’s review, given that the noise and vibration issues may not have been identified, let alone resolved?
This debate is about the future of the Ajax programme. Although the near future revolves around the resolution of the immediate issues that followed Exercise Titan Storm, beyond that the programme will need to achieve full operating capability, but crucially, it will be the tip of the spear in our armoured doctrine. So, a good start would be to have an armoured doctrine that is coherent.
In 2014, we ordered 589 vehicles out of an optional 1,328—below the Army’s required fleet size at the time of 686. Although that was not necessarily a defining error at the time, subsequent decisions, even as recently as last summer, have compounded the issue, bringing us to a situation where our armoured fleet is now completely unbalanced—increasingly so given the evolution of modern conflict since the Russian invasion of Ukraine, the ubiquity of drones at all levels, and the current global arms race.
When Ajax was commissioned, we were still undertaking combat operations in Afghanistan. Since then, we have had multiple defence reviews, and changed our focus to the Indo-Pacific and now to the High North, and now we are talking about putting troops in eastern Europe as a deterrent to a belligerent Russia. The irony is that we still have much of the same armour designed to do that job the first time round.
The original plan was for Ajax, alongside Boxer and Challenger 3, to provide the backbone of the Army’s armoured capability within Integrated Force 2030. March 2021’s “Defence in a Competitive Age” outlines how the Army would use Ajax in its two close-combat armoured brigade combat teams, and as part of its deep reconnaissance strike brigade combat team—formations that are now putatively in place.
We cannot discuss the future of the Ajax programme without discussing how the Army plans to use Ajax within those brigade combat teams. As somebody with a background in armoured infantry, who formerly held an admittedly niche specialisation in anti-tanks, I have more than a keen interest in the future of our armoured capability. Being something of a tank-spotter, I note some glaring capability gaps based on the information provided by Ministers over the past year or so.
Let us start with the basics. In December 2024, the right hon. Member for Liverpool Garston (Maria Eagle), the then Minister of State for Defence Procurement and Industry, stated in a written answer to my question:
“On current plans, Boxer will be delivered to four Heavy Mechanised Infantry Battalions and Divisional Enablers.”
Seven months later, however, on 15 July, she stated:
“The Army intends to reorganise its Heavy Forces units in 3 Division, such that all four would become Armoured Infantry Units based on the Ajax and Boxer family of vehicles.”
She subsequently went on to state:
“The Army intends to equip the Regular Infantry Units within 3 (UK) Division with Ares in the infantry troop carrying role: 1 Mercian, 1 Royal Regiment of Fusiliers, 1 Royal Welsh and 5 Rifles.”
What happened between December 2024 and July 2025 that saw such a fundamental change to the future of the infantry, and indeed our entire armoured capability? The number of Ares platforms to be provided has not changed since 2014: just 93. For reference, the current land equipment table shows that we currently have 604 Warrior. Ares’s role was originally “protected mobility reconnaissance support” and latterly to “deliver and support specialist troops”. It has never once been earmarked as an infantry-fighting vehicle.
The present Minister for Defence Readiness and Industry, the hon. Member for Plymouth Sutton and Devonport (Luke Pollard), then gave this written response to my question:
“The Ares variant of Ajax is designed for mounted close combat and is being delivered to the Field Army. The decision to field Ares with Infantry Battalions was taken after a considerable assessment programme.”
I would be interested to know whether the aim of the Ares assessment programme was simply to justify the existing total of 589 vehicles, or actually to highlight the capability required, because whichever question the Army asks, the answer always appears to be 589 Ajax vehicles. I asked to see the outcome of that assessment programme but was told that its disclosure would
“be likely to prejudice the capability, effectiveness or security of the Armed Forces”.
I suggest that, given the enemy knows that Ares does not have any armour-defeating weapons capability, the issue around prejudicing capability lies elsewhere.
Let’s walk that back a step. In my opinion, the Ares variant is not designed for mounted close combat. It is equipped with a remote weapon station that can mount a 50-calibre machine gun at the heaviest. As someone whose specialisation in the Army was armoured infantry, I know my way around a 30 mm canon. A 50-cal cannot defeat armour; it is no substitute for 40 mm APFSDS, which is the round that its Ajax brother uses.
In September, the hon. Member for Plymouth Sutton and Devonport stated in a written answer that Ares would be,
“used to deliver and support specialist troops across the battlefield. The term ‘specialist troops’ is used informally, and in this context refers to Anti-Tank Javelin Teams, Snipers and Support Troops.”
But by November that had changed again, with the same Minister contradictorily stating:
“Anti-tank platoons within Armoured Infantry units will be equipped with Boxer variants”.
So which is it: Ares or Boxer for Javelin platoons? Will armoured infantry battalions be tracked or a mix of wheeled and tracked, with the logistical implications of that? Will Royal Electrical and Mechanical Engineers light aid detachments have both Ajax and Boxer repair and recovery variants? Where are we going to keep the additional vehicles? What is the training burden of mixed armoured fleets, thereby doubling driving cadres, maintenance training, and vehicle commanders’ courses? Have we even bought a recovery variant of Boxer yet? The Army’s own website suggests it is not one of the variants within the 623. This approach is incoherent and suggests that the Army does not really know what to do with the capability it will shortly have.
“As the ARES platform is delivered into service, tactical doctrines will be reviewed accordingly.”
I do not expect the Minister to answer the question or to know the ins and outs of armoured infantry doctrine, but he should raise the question with the Land Warfare Centre, and with the infantry battalions that will receive Ares, to ask them how the platform will be used and what capability will then be lost.
By removing a main armament from the armoured infantry’s firepower we fundamentally change the way that the vehicle is fought. It changes the way the vehicle can move cross-country, effectively removes the option to move in bounding overwatch, and means it can never engage enemy armour. Doctrinally, it turns the armoured infantry into mechanised infantry.
Doctrinally, Ares is more akin to the Mk3 Bulldog. Despite that, the Minister for Defence Readiness and Industry this week informed me that Ares
“is more suitable to be employed in the direct battle, rather than in the close support role”.
Given the glaring absence of a main armament on Ares, I would dispute that assessment, which seems convenient rather than well thought through. Bulldog itself is due to be replaced in 2030, so what progress has been made in procurement of the Patria 6x6?
Crucially, in December, the same Minister stated:
“There are no other platforms within the Army’s armoured fleet which can fulfil the armoured reconnaissance role; Ajax has been specifically designed for this purpose.”
With that in mind, and given that the entire Ajax fleet is grounded for an unspecified length of time pending an investigation by the Defence Accident Investigation Branch, with support from the Army Safety Investigation Team and General Dynamics, can the Minister state how the armoured reconnaissance capability of the British Army is currently being provided given that statement, and therefore what is the deployability of 3rd (UK) Division without any formation or armoured reconnaissance capability, or even the deployability of an armoured battle group from within 3 Div?
The parlous state of the British Army’s armoured capability is on the cusp of being thrust into stark relief by the Prime Minister’s announcement last week that we had committed troops to the multinational force for Ukraine. While any detail on that force structure is currently pure speculation, it was reported by The Times that those troop numbers would not exceed 7,500. On a three-form cycle, that is circa 22,000 troops—the majority of the field army. If they are to be more than a speed bump for the vanguard of the Guards Motor Rifle Brigade, they will need capability that they simply do not have today.
Challenger 3 has no timeline, with manufacturing due to commence only once the tank’s performance has been proven in the demonstration phase. It is not going to appear anytime soon. The Government have no plan for the remaining 140 Challenger 2s that are not due to be upgraded, and not even a promise that the plan will be outlined in the mythical defence investment plan. That is against the backdrop that the defence investment plan is unfunded, with a black hole of somewhere around £20 billion, give or take an Ajax programme budget. There will be cuts, and there will be delays. Out-of-service dates are going to be stretched to their limits. Bulldog is already 63 years old, and I am sure that it is no coincidence that it will be 67 when it reaches its out-of-service retirement date.
The Chief of the General Staff wants to implement the 20-40-40 land warfare concept, of which Ajax is a key part, working in tandem with Project Asgard. That is the capability that could and should provide a continuous on-land deterrent along the eastern flank defensive line, reduce our sensor-to-effector time, and achieve the nebulous tenfold increase in lethality by reducing the kill chain to well inside thesub-seven-minute timeframe that defines the current frontline in Ukraine.
Ajax cannot be scrapped. The Army needs it. There is no plan B, and given that it is a fixed-price contract, scrapping it will save no money anyway, despite Ministers confirming that the Government have sought legal advice from the Government Legal Department. The Government have not even considered a viable alternative option in CV90, and starting that process from scratch will take the best part of a decade before we even see a vehicle, based on current queues.
Put simply, Ajax needs to be delivered, primarily because the Army needs to restore its armoured reconnaissance capability. Additionally, there is a second order effect: confidence. The British Army badly needs to restore faith in Ajax as a platform. For all the negative stories and press, the Army and the Government must work out how to rebuild confidence in their ailing platform. I know what it is to be given kit that I do not have confidence in, and to have to use it on operations and wonder whether it will let me down, or worse. I know that the Minister can sympathise with that view. We must restore faith in the platform, not only for the soldiers expected to operate with it, but for its appeal from an investor and export position.
The long-term future of Ajax depends on the ability of General Dynamics to sell it overseas. The most advanced armoured fighting vehicle in its class should be an easy sell to the nations currently in the process of rearming and upgrading. We have a history of exquisite sovereign capability that nobody else really wants: Challenger 2, Warrior, even the SA80. Each of those has suffered from a lack of development over its life cycle, too often a day late and a dollar short.
The Government have not just failed in supplying our armed forces with the tools they need to keep us safe. In repealing the protections put in place by the previous Government’s Northern Ireland Troubles (Legacy and Reconciliation) Act 2023, for example, they are opening the door to another wave of prosecutions against those who have previously served. How can all of that be the right way to treat those who have risked their lives to keep us safe? What message does it send to those who might consider enlisting in the future? What other country would treat its former service personnel with such disregard?
Ajax does not tell the whole story, but it is one recent and important example. How the Government choose to proceed from here will send a signal to those who are serving, and those who might serve in the future, about whether their Government intend to uphold their side of the bargain. Regardless of political party, we should all want our armed forces to know that we support them, not just with words, but materially. I hope the Minister will provide some clarity on when we can expect a final verdict on Ajax, and what steps the Government are taking to ensure that future procurement is faster, more cost-effective and safer for those who are serving. That is the very least that our armed forces deserve.
I will touch briefly on defence exports. We must learn lessons from those abroad, particularly Leopard, which is a main battle tank. That platform was modular, upgradeable and interoperable, which meant it was a much stronger prospect for our defence export. When it comes to procurement, we should always bear defence exports in mind.
There are wider lessons too for the forthcoming defence investment plan, which must make a decisive break. We need a system that is capable of designing and testing earlier on, rather than one that rushes into production in the hopes that problems can be fixed later on. Ajax must be a turning point, not just for this vehicle, but for how we procure defence capability in this country in the future.
My hon. Friend the Minister is one of the most impressive forces in British politics; if he can climb Mount Everest in just five days—to raise money for our veterans, no less—I have no doubt about his ability to get to grips with one of the most challenging problems facing defence procurement today.
There is also a significant reputational risk for our Government if we deploy those systems without adequate protection, especially given those reported threats. I thank you, Mr Stuart, for allowing me to mention that within this wider debate. Could the Minister use his powers to speed up the conversation that my local constituency business is hoping to have with senior figures, including the Minister for procurement, to ensure that we, at speed, learn from the lessons of Ajax and apply them as we are spending multimillions of pounds of our money at a considerably risky time in the international landscape. We may not be able to change the direction of a tanker—I appreciate it is a big job—but if we do not take this new information seriously we risk having another debate like this one, but on a different topic, in the future.