I beg to move,
That this House has considered junction 10A on the A14 at Kettering.
May I say what a pleasure it is to see you, as such a distinguished and experienced member of the Panel of Chairs, in the Chair for our proceedings today, Sir Gary? I thank Mr Speaker for granting me this debate, and welcome the Minister to his place; he is an assiduous, diligent, hard-working and energetic Minister, and I am sure that he will listen closely to my constituents’ concerns.
This is not the first time that the House has heard about junction 10A on the A14. I have asked a series of oral and written parliamentary questions, and have had two debates in this Chamber on the same subject—in November 2020 and February 2023. I suspect junction 10A is unique amongst the road projects that the Department for Transport is considering, because it has three defining characteristics: originally, the scheme was in the road investment strategy 1 for the period 2015 to 2020 and it has now been resubmitted for RIS3; it is 50% developer funded; and it has a benefit-cost ratio of 3:1. Those are all impressive and unique characteristics that make the scheme distinct.
I also know that the scheme has the personal attention of the Secretary of State for Transport himself, because I met him in March last year and he was kind enough to write to me to say:
“I was taken with the fact that”
junction 10A is
“significantly developer-funded, had a high benefit-cost ratio, and was originally scheduled for RIS1.
As a result, I am happy to continue progressing the scheme as previously planned during the RIS3 period, subject to business case.
I also agree with your suggestion that National Highways and DfT officials should cooperate intensively with the local planning authority and the developer to progress the scheme as quickly as possible.”
Given the many items that the Secretary of State has to deal with every day, I am pleased that he has personally taken an interest in the scheme.
I know that the Minister knows Kettering: in his previous guise as Pensions Minister he was kind enough to visit in summer 2022 to support our local older persons’ fair in the Corn Market Hall in Kettering, as part of the drive to encourage pensioners to take up pension credit. I thank him for his interest and for having already visited Kettering.
Junction 10A does not actually exist—at the moment it is just a blob on a DFT map—but it is a junction that local residents very much need if Kettering, Barton Seagrave, Burton Latimer and Cranford are not to grind to a halt because of all the traffic generated by the new house building taking place locally.
In short, junction 10A is critical road infrastructure. Originally, it was set to cost £40 million—the figure is probably is now nearer to £60 million or even more—with financial contributions split between the DFT and the developer, and it is required to deliver phase 2 of the Hanwood Park development which, in Government planning terms, is designated as a garden community that will comprise an eventual 5,500 dwellings and employment land covering 328 hectares to the east of Kettering. Local land values will not allow the junction’s development to be funded without Government intervention, so public funding is required.
In line with planning conditions, junction 10A must be in place by the time that between half and two thirds of the dwellings on the development are occupied. Just under 1,400 dwellings are already occupied, and the developer’s current housing trajectory shows that the dwellings trigger for the junction will be reached some time in 2026 or 2027. There is therefore a significant risk that without the new junction the development will grind to a halt in three or four years’ time, so my ask of His Majesty’s Government and the Minister today is for a firm commitment to include junction 10A in the Department’s road investment strategy 3, which is the programme for major road programmes in the period from 2025 to 2030. Junction 10A is already in the pipeline for RIS3, but we now need a definite funding commitment to include it.
The continuation of the sustainable roll-out of the Hanwood Park development can happen with confidence only if there is a definite Government commitment to the junction and a tangible Government commitment to the funding. What we are talking about is the need for joined-up government. If His Majesty’s Government are to get anywhere near their objective of 300,000 new dwellings built each year in England, they need to ensure that the requisite roads infrastructure is in place. The funding of junction 10A and the enabling of Hanwood Park to continue to be developed beyond 2026-27 will be a key test of the dovetailed Government housing and road strategy.
I know that the DFT already recognises the importance of the junction, because funding for it was originally included in RIS1 for the 2015-to-2020 period. The slow roll-out of housing development amid the national economic conditions at the time meant that the programme was not activated then, but housing development on the site is now proceeding at pace, with up to 400 new dwellings a year, and the funding commitment is now required.
Importantly, the Hanwood Park development is the fourth largest sustainable urban extension in the whole country. It is one of the nation’s flagship housing extensions and sits within the strategic Oxford to Cambridge planning arc. For local people, the Hanwood Park development is the equivalent of bolting on to the town of Kettering itself another town the size of Desborough. We have to ensure that the homes built on the development form a vital, liveable community and do not simply become one big, soulless housing estate. To make that happen, we must ensure not only that the infrastructure is in place to serve those new dwellings, but that there is no adverse impact on the quality of life of existing residents in other parts of Kettering, Barton Seagrave, Burton Latimer and Cranford.
Outline planning permission was originally granted in April 2010 for 5,500 houses; a range of employment uses; a mixed-use district centre, including shops, local services and a health clinic; three local centres; a secondary school; four primary schools; hotel and leisure development; and extensive formal and informal open spaces.
Work is well under way to deliver development in the first phase of Hanwood Park, with 2,117 homes benefiting from reserved planning matters approval, and these are either built out, currently under construction or about to be commenced. Reserved planning matters approval has also been given for roads, green spaces, sustainable urban drainage systems and utilities infrastructure. Hayfield Cross Church of England Primary School—the first school on the site—is fully operational and serves the needs of Hanwood Park and the surrounding area. A free school bid has been successful for the delivery of the secondary school.
Despite the challenges of the pandemic and the associated economic downturn, delivery continues across the scheme, with David Wilson Homes, Barratt, Bellway, Orbit, Persimmon, Avant, Taylor Wimpey and Grace Homes, which is a local small and medium-sized enterprise house builder, progressing on site. As of early December 2023, about 1,126 dwellings were occupied, with a further 300 under construction. This includes the successful delivery of more than 20% affordable housing, which meets a key requirement of local housing needs, as well as more recently adapting to changes in the energy system, with the latest developer at Hanwood Park, Grace Homes, delivering 100% electrically heated and powered homes, which are well insulated and using heat pumps ahead of the introduction of the future homes standard.
Further confidence has been expressed in Hanwood Park, including proposed investment in non-residential facilities, including for a health centre and an anchor food store. These investments will be subject to receipt of planning permission, which in turn requires progress to be made on the junction 10A road scheme. The fact that such investment has been made—in effect, conditional on securing the junction improvement—places an increased focus on the RIS3 programme and demonstrates again the strong fundamentals in place at Hanwood Park and the additional benefits that the RIS3 investment will bring.
Hanwood Park is also proposed as the site of a much needed mixed-sex secondary school, which His Majesty’s Government have done much to support. The delivery of the school is also, in practical terms, contingent on the junction project being committed to.
The rate of delivery during the past few years, including throughout the pandemic, has at times reached an impressive 400 units a year. This, against a backdrop of mixed performance elsewhere in the country, demonstrates the significance and substantial contribution that Kettering can make to the UK’s growth prospects.
A new outline planning application has been submitted for the remaining 3,383 dwellings, as well as the remaining schools, formal and informal open spaces, district and local centres, a hotel and employment. The application has reached an advanced stage, with North Northamptonshire Council’s planning committee targeting this spring, in a few months’ time, for a decision on it—but certainty on junction 10A is critical to the scheme.
The development of Hanwood Park forms a key component of housing to be delivered in North Northamptonshire and Kettering in the adopted “North Northamptonshire Joint Core Strategy 2011-2031”. Housing growth will be in parallel to the delivery of employment land and other uses. The development as a whole is estimated to create an amazing 8,100 new local jobs. Without a Government commitment to junction 10A, 2,000 new homes, including 400 affordable ones, simply will not be delivered. Without junction 10A, there would be significant and unacceptable traffic congestion at the existing junction 10 roundabout and elsewhere, as well as untenable residential amenity issues caused by large vehicles accessing the employment uses located in the south-eastern area of the new development. That means that the traffic would be forced to travel through the new residential areas.
In addition to the continued housing delivery, the new junction will unlock employment land, which is key for local sustainable growth. The new junction is essential in enabling the delivery of some 10 hectares of employment land in the south-eastern quadrant of the development. The market delivery of those employment sites would be extremely challenging and may not be possible without junction 10A. The same position is true of land situated in and around junction 10A. There is therefore a significant risk that the development as a whole will grind to a halt. Thousands of jobs could be at risk, and further homes simply will not be built.
At the moment, 2026 remains the target date for the delivery of junction 10A, in line with the DFT’s RIS3 programme, but that requires detailed planning approval to be achieved and procurement to commence concurrently. That can happen only if there is confidence in the Government’s commitment to junction 10A and a tangible commitment to RIS3 funding. Hanwood Park now faces the unwelcome prospect of beginning to halt the development in the next two years unless there is clear and unambiguous confidence in the ongoing support for the project. The challenge will increasingly become a question of supply rather than demand, as there are a little more than 700 homes left to construct and occupy.
Against that backdrop, local residents on site are becoming increasingly frustrated by the lack of delivery of further amenities and facilities, which is leading to more journeys by car to alternative locations to meet basic needs and undermines the principle of the original sustainable urban extension programme. Any further loss of momentum will damage long-term confidence in the scheme and create discontent among the new residents, who are beginning to question whether it will ever be completed. Developers and investors alike need as much certainty as possible to be able to plan and have confidence in the route ahead, and recent progress is now in danger of stalling.
I know that National Highways is progressing junction 10A through its approval processes and considering the part-funding solution for the new junction. North Northamptonshire Council is fully engaged and supporting the process, together with the developer of Hanwood Park. My view is that the process now needs to be expedited so that there is certainty around the delivery of the new junction, which is critical to the delivery of Hanwood Park as a whole. A firm commitment to RIS3 funding is now imperative to ensure continued housing delivery, including vital affordable housing, along with the significant employment opportunities and economic growth that the local area needs, and to give the market confidence that delivery will not be stifled.
I invite the Minister, on one of his regional road tours, to come and see Kettering for the second time in his ministerial career and to see the site of the proposed new junction. For local people, the tragedy is that we could have had as many as 3,500 new homes built on Hanwood Park without the necessary road infrastructure to take us beyond that level. That presents the real risk of gridlock in the town of Kettering, with initial houses already provided but the Government not coming up with their share of the funding for the new junction 10A.
My plea to my hon. Friend the Roads Minister, on behalf of local people in Kettering, is that he recognise the fundamental importance of the new junction to people in the local area, and that the Government make the commitment to fund it that we badly need and expedite the process to deliver the junction on the ground.